Anson Resources and Koch Technology Solutions Collaborate on Pilot Testing at Green River

In This Article:

Pilot unit production is expected to commence in July 2024

Highlights:

Anson Resources has signed an agreement with Koch Technology Solutions for testing of a Li-Pro™ Lithium Selective Sorption (LSS) pilot unit using brine from the Green River Lithium Project.

The pilot unit will be located on Anson Resources' 100% owned private land at Green River and process fresh brine under commercial production conditions from Bosydaba#1 well into lithium chloride, that may be used to produce battery-grade lithium carbonate.

The pilot unit results will be used for process optimisation and product verification for a proposed commercial scale plant. Results will provide important inputs for a full-scale Li-Pro™ unit within Anson Resources' planned lithium extraction facility.

Pilot unit production is expected to commence in July 2024.

Anson Resources and KTS have agreed on a cost sharing framework involving an investment by KTS through a convertible note to cover the Green River Lithium Project piloting development.

NEWPORT BEACH, CA / ACCESSWIRE / June 23, 2024 / Anson Resources Limited (ASX:ASN ) (" Anson Resources " or " the Company ") is pleased to announce its collaboration with Koch Technology Solutions ("KTS"), a Koch Engineered Solutions ("KES") company, for the commissioning of its Li-Pro? process pilot unit for lithium extraction at the Company's Green River Lithium Project ("Project") in Utah, USA. The pilot will be jointly funded by Anson Resources and an investment from KTS through a convertible note as the companies work to develop a further commercial relationship.

KTS completed their detailed treatability study in May 2024 using brine from Anson Resources' Green River Lithium Project. KTS' testing has indicated exceptional results for lithium recovery and element rejection rates and suggests superior results to those achieved in Anson Resources' Definitive Feasibility Study, see ASX announcement 8 September 2022 . The Company is in the process of determining any revisions to CAPEX and OPEX from the results achieved.

Through an agreement completed on 21 st June 2024, the companies will partner to expedite the commissioning of the pilot unit. Results from the pilot unit, if successful, will provide detailed feasibility engineering and cost data for deployment of the full-scale Li-Pro? process at the Green River Lithium Project's lithium extraction facility.

The pilot unit is expected to be operational in July 2024 at Anson Resources' private land in Green River, Utah and will run 24 hours a day, 7 days a week for the next two to four months. The unit will process fresh brine from the Company's Bosydaba#1 well into lithium chloride, replicating commercial production conditions. This pilot unit is in addition to Anson Resources' operational sample demonstration plant ("SDP") at Green River that utilises the existing flow sheet , see ASX announcement 15 April 2024. The two direct lithium extraction ("DLE") technologies will be tested concurrently using brine from the collected during the drilling program of the Bosydaba#1. Test results of the brine collected from the Leadville Formation, Mississippian Units indicated that lower levels of contaminants, higher porosity, and higher pressure than at the Paradox Lithium Project, see ASX announcement 20 th May, 2024.