ARIS MINING REPORTS Q3 2024 GOLD PRODUCTION, UPDATES SEGOVIA RESERVE AND RESOURCE ESTIMATES AND EXPANSION MILESTONES

In This Article:

VANCOUVER, BC, Oct. 7, 2024 /PRNewswire/ - Aris Mining Corporation (Aris Mining or the Company) (TSX: ARIS) (NYSE-A: ARMN) announces gold production results of 53,608 ounces (oz) for Q3 2024, with 47,493 oz from Segovia and 6,115 oz from the Marmato Upper Mine. This represents a 9% increase over total gold production in Q2 2024.   Additionally, the Company has made significant progress on expansion projects at Segovia and has updated mineral resource and mineral reserve estimates with an effective date of July 31, 2024.  At the Marmato Lower Mine, construction is advancing on schedule and has crossed the 25% spend threshold.

Neil Woodyer, CEO of Aris Mining, commented "We are pleased to share the continued progress of our Segovia and Marmato expansion projects, which position Aris Mining to achieve an annual gold production rate of approximately 500,000 oz in the second half of 2026. The first phase of the Segovia Expansion, which includes an expanded receiving area for mill feed from our mining partners, has been successfully commissioned. Phase 2 of the Segovia Expansion is underway and is on track for completion in Q1 2025. Following completion and ramp-up, Segovia's gold production is expected to exceed 300,000 oz per year. This growth is driven by a focused exploration strategy that has consistently increased gold resources and replaced gold reserves.  Additionally, construction of the Marmato Lower Mine remains on schedule, and we continue to advance the studies for the redesigned and smaller environmental footprint Soto Norte project for early 2025."

Segovia – Expansion updates

Phase 1 of the Segovia expansion is complete with the newly expanded receiving area for our contract mining partners (CMPs) fully commissioned and being handed over to operations.  The expanded receiving area enhances mill feed capacity and operational efficiencies. Phase 2, which involves installing a second ball mill in the former contractor receiving area, is underway and scheduled for completion in Q1 2025. The new ball mill will increase throughput and enable finer grinding, process efficiency and gold production.

Gold production from Segovia in Q3 2024 totaled 47,493 oz, reflecting a 9% increase over Q2 2024.  With the expansion ramp-up in mind, Aris Mining is targeting gold production from Segovia of 185,000 to 195,000 oz in 2024, 250,000 oz in 2025 and over 300,000 oz in 2026.

Segovia – Updated Mineral Resource and Mineral Reserve Estimates

As announced in our August 2024 exploration drilling results news release1, Segovia's exploration programs continue to deliver high-grade intersections. These results are included in updated estimates effective July 31, 2024, resulting in growth of the mineral resources and full replacement of the mineral reserves (see Figures 1 and 2 below).  These new estimates build on the strong growth in 2023 and support the ongoing Segovia expansion project. The 2025 drilling program is expected to focus on these newly identified near-mine mineral resources, aiming to convert them into mineral reserves with low development costs.