Cerro de Pasco Resources closes first tranche of $1.8M equity financing, provides update on Land Easement Application Process for Quiulacocha Tailings

Cerro de Pasco Resources
Cerro de Pasco Resources

In This Article:

NOT FOR DISSEMINATION IN THE UNITED STATES OR FOR DISTRIBUTION TO U.S. NEWSWIRE SERVICES

MONTRéAL, Nov. 20, 2023 (GLOBE NEWSWIRE) -- Cerro de Pasco Resources Inc. (CSE:CDPR) (OTCPK: GPPRF) (FRA: N8HP) (“CDPR” or the “Company”) has closed a first Tranche of its previously announced non-brokered private placement, for total aggregate gross proceeds of $ 1,772,000 (the "Offering").

CDPR also confirms that it is currently addressing final requirements in relation to a two-year Legal Easement (“Easement”), providing access to the surface areas corresponding to CDPR’s El Metalurgista Concession and the Quiulacocha Tailings Project (“QT Project”). The Easement, enabling the Company to perform confirmatory exploration via a 40-hole sonic drilling program, is expected to be passed by Supreme Resolution in December 2023.

Easement Process

The Easement process was initiated by CDPR on 25 August 2022 with the authority and guidance of the General Mining Bureau (“DGM”), the organic unit within the Ministry of Energy and Mines (“MINEM”) responsible for formulating technical standards and issuing opinions related to mining permits and authorizations. Audiences were held between CDPR and Activos Mineros SAC (“AMSAC”), as further described below, who control surface rights over the entire QT Project area. Having confirmed AMSAC’s rejection of a voluntary land easement, DGM endorsed the initiation of a Legal (or “Forced”) Easement process.

The process recognizes that CDPR owns an irrevocable and indefinite right to explore and exploit the El Metalurgista concession, covering the Quiulacocha Tailings.

Easement Approvals

Approvals were obtained from four ministries including 1. Energy and Mines, 2. Environment, 3. Housing and Construction, and 4. Agriculture. With the file complete, CDPR had expected DGM to draft a Supreme Resolution granting the Legal Easement in August, for signature by the MINEM Minister and the President of the Republic in September 2023.

Delays

However, delays have been incurred as a result of two separate and consecutive appeals by AMSAC. The first was reviewed by the independent Mining Council, and duly resolved by DGM. The second, filed on 19 September 2023 and likewise relating to formal matters is currently in process, due to be assessed by the Mining Council on November 30th, following which the Council is expected to issue a definitive ruling in favor of the Easement.

Timeline

As a result of delays caused by the AMSAC’s appeals, the Supreme Resolution is now expected to be submitted for signature in December.