DLP Resources Intersects 954m of 0.36% CuEq* and 94.00m of 0.81% Cu on the Aurora Project in Southern Peru

In This Article:

Cranbrook, British Columbia--(Newsfile Corp. - September 26, 2024) - DLP Resources Inc. (TSXV: DLP) (OTCQB: DLPRF) ("DLP" or the "Company") announces receipt of complete drill results for drillholes A24-017 and A24-018 on the Aurora porphyry copper-molybdenum-silver project in southern Peru. (Figure 1).

Results for the first sixteen drillholes, were last released between January 04 and August 15, 2024 (see DLP Resources Inc., news release of January 04, 2024, June 25, 2024 and August 15, 2024 for results for the previous sixteen drillholes).

Highlights

Drillhole A24-017 was drilled off a drill platform approximately 169m northeast of A22-003 with the aim of expanding the copper mineralization further to the east. This drillhole intersected copper mineralization from surface extending to 125m in mineralized hornfels. Results were as follows:

  • 0.63% Cu over 125m from 0.00m to 125.00m.

  • 0.81% Cu over 94.00m from 31m to 125.00m.

Drillhole A24-018 was drilled off the same platform as the vertical hole A23-013 but drilled at -70 degrees to the south. The purpose of this hole was to expand the copper-molybdenum-silver mineralization towards the southwest side where the limits of mineralization are still uncertain. Results for this hole were as follows:

  • 0.36% CuEq* (0.23% Cu, 0.02% Mo, 2.09g/t Ag) over 954m from 164.00m to 1118.00m.

The complete set of results for A24-017 and A24-018 are summarized in Table 1 below.

Mr. Gendall, President and CEO commented: "A24-017 confirmed shallow copper mineralization in the northeast with A24-018 expanding the footprint of copper-molybdenum and silver mineralization in the southwest side of Aurora. We continue to have success with the expansion drilling at Aurora and we look forward to results from further planned drilling in the southeast".

Aurora Cu-Mo Project - Summary of Drill Results for A24-017 and A24-018

  • Drill hole A24-017 (Figures 2 and 3) commenced on June 24th at an inclination of -70 degrees on an azimuth of 085 degrees. and ended on August 15 at 987.25m. Summary geology is as follows:

    • 0 - 125.00m: Mineralized hornfels with copper enrichment.

    • 125.00m - 987.25m: Weakly mineralized hornfels.

  • Drill hole A24-018 (Figures 2 and 3) commenced on July 23rd at an inclination of -70 degrees on an azimuth of 185 degrees. and ended on August 29 at 1118.00m. Summary geology is as follows:

    • 0 - 113.50m: Mineralized hornfels with chalcopyrite, chalcocite and covellite within the enrichment zone.

    • 113.50m - 429.80m: Mineralized quartz-eye-feldspar porphyry.

    • 429.80m - 491.30m Mineralized quartz-eye-feldspar-biotite porphyry with intercalated mineralized hornfels

    • 491.30m - 1118.00m: Mineralized hornfels with occasional mineralized porphyry dykes of between 2m and 8m in width.