DYLLF: Deep Yellow Issues Quarterly Report – Review of recent achievements as company continues to proceed toward expected production at Tumas (Namibia) in 2026; The spot price of uranium exceeded US$100/lb. during January 2024.

In This Article:

By Steven Ralston, CFA

OTCQX:DYLLF | ASX:DYL

READ THE FULL DYLLF RESEARCH REPORT

Deep Yellow Ltd. (OTCQX:DYLLF) (ASX:DYL) is unique among junior mining companies: the company is being positioned to provide a leveraged opportunity to participate in all phases of the expected upswing in uranium prices. Management’s Dual Pillar strategy is designed to deliver both organic and inorganic growth by advancing the company’s Namibian and Australian projects through the production stage and by acquiring additional projects as the industry consolidates. Management is focused on becoming a low-cost, Tier I uranium producer, defined as a multi-project producer of uranium with the capacity to deliver 5-10 million lbs. of uranium annually.

QUARTERLY ACTIVITIES REPORT

Deep Yellow recently filed its Quarterly Activities Report for the period ending December 31, 2023.

Tumas Project Update

A Mining License (ML 237) was issued by the Namibian Ministry of Mines and Energy issued Mining , which is valid September 21, 2043. This is a significant milestone that allows Deep Yellow to continue to advance toward production.

A Definitive Feasibility Study Re-Costing Study was completed, which updated the base case price of uranium to US$75/lb. from US$65/lb. U308 (a conservative increase considering the spot price has exceeded US$100/lb.) and adjusted the initial cost estimates to reflect the moderating rate of inflation and an abatement of the supply chain pressures. The base case IRR increased from 19.2% to 27.0%.The Re-Costing Study continues to validate the commercial viability of the Project.

Between late March and mid-August 2023, Deep Yellow completed a 235-hole (8,017m) RC drill program that targeted areas west of Tumas 3 East and Tumas Central. 109 holes explored for additional resources (spaced lines between 200m to 1,000m) and 126 holes focused on expanding the current resource, along line and holes spacing of 100m. Based on the results of the drill program, the Indicated MRE increased 10.4% from 54.9 Mlb at 320 ppm eU308 to 60.6 Mlb at 325ppm eU308. The Inferred MRE increased 24.0% from 5.0 Mlb at 219 ppm eU308 to 6.2 Mlb at 170ppm eU308.

Management continues to identify additional resources through drilling programs in order to achieve its goal of extending the LOM of the overall Tumas Project to over 30 years from the current level of 22.5 years.

The timeline for the Final Investment Decision is being maintained with the FID expected to be made during the third calendar quarter of 2024.

Mulga Rock Project Update

In late October, management provided an update on the metallurgical test work program being conducted for the Mulga Rock Project (Western Australia). Thus far, the results are encouraging that critical minerals (base metals and rare earth elements) will be able to contribute additional value to the uranium resource.