The Enefit Green group’s operating income for Q2 2024 decreased by 7% while operating expenses (excl. D&A) decreased by 12% compared to the same period last year. As a result, EBITDA decreased by 2% to €19.3m. Net profit for the quarter increased by €2.8m to €3.9m (earnings per share €0.015).

Andres Maasing, interim chairman of the management board of Enefit Green comments:

"Construction activities are underway in several development sites, including three large wind farms in Estonia and Lithuania, with a total capacity of 422 megawatts. Investments during the last quarter exceeded a tenth of our total ongoing investment programme. The volume of investments required to complete all ongoing constructions is close to €250m.

In the Sopi-Tootsi wind farm, 25 of the 38 wind turbines have been erected, and the installation of the remaining turbines is proceeding as planned. In the solar farm, which we are building in the close vicinity, installation of the panel frames is about to be completed and the installation of the panels is already ongoing. In Lithuania, in the Kelm? I wind farm all 14 wind turbines have been erected, and turbine foundations are being built in the Kelm? II wind farm. In Latvia, we are building our first solar farms. We expect to start generating electricity in all these projects later this year, except for the Kelm? II wind farm, which will take longer to complete.

In the second quarter, we produced 358 gigawatt-hours of electricity (+35% y-o-y) and 96 gigawatt-hours of thermal energy (-27%). The significant increase in electricity production for several quarters in a row is due to the production from both wind and solar farms already commissioned and from those still under construction. During the last year and a half, a total of eight new projects have started generating electricity, of which five have been commissioned and three are nearing the end of construction.

The contribution of new production assets in our production portfolio is gradually growing, but the achievement of the electricity production target has been primarily affected by lower wind speeds and the configuration activities of new wind farms (especially in the Tolpanvaara wind farm). The performance indicators for the quarter were affected by lower market prices of electricity and higher-than-expected output.

We continue to focus on completing ongoing construction projects on time, maintaining high availability, and working to bring storage and hydrogen technologies to market."


Webinar to present the results of Q2 2024

Today, 1 August 2024 at 13.00 EEST Enefit Green will host a Webinar in English to present and discuss its Q2 2024 results. To participate, please follow this link.