Entrée Resources Announces Second Quarter 2024 Results

Entree Resources Ltd
Entree Resources Ltd

In This Article:

VANCOUVER, British Columbia, Aug. 07, 2024 (GLOBE NEWSWIRE) -- Entrée Resources Ltd. (TSX:ETG; OTCQB:ERLFF – the “Company” or “Entrée”) has today filed its interim financial results for the second quarter ended June 30, 2024. All numbers are in U.S. dollars unless otherwise noted.

Q2 2024 HIGHLIGHTS
Oyu Tolgoi Underground Development Update
The Oyu Tolgoi project in Mongolia includes two separate land holdings: the Oyu Tolgoi mining licence, which is held by Oyu Tolgoi LLC (“OTLLC”) and the Entrée/Oyu Tolgoi JV Property, which is a joint venture partnership between Entrée and OTLLC. Rio Tinto owns 66% of OTLLC and is the manager of operations at Oyu Tolgoi.

  • On July 15, 2024, Rio Tinto announced ramp up of the Oyu Tolgoi Lift 1 underground mine continues in line with its long-term plan. Oyu Tolgoi is set to become the world’s fourth largest copper mine by 2030 with the operation expected to deliver average mined copper production of ~500 thousand tonnes per annum between 2028 and 2036.

  • OTLLC continues to see strong performance from the Lift 1 underground mine, with a total of 114 Lift 1 draw bells opened from Panel 0 on the Oyu Tolgoi mining licence, including 14 draw bells during the quarter ended June 30, 2024. In the second quarter 2024, OTLLC delivered 1.5 million tonnes of ore milled from Panel 0 on the Oyu Tolgoi mining licence at an average copper head grade of 2.02%.

  • The sinking of ventilation Shafts 3 and 4 was completed in April with the shafts reaching their final depths of 1,130 metres and 1,176 metres below ground level, respectively. Rio Tinto continues to expect both shafts to be commissioned in the second half 2024.

  • As at June 30, 2024, construction of the conveyor to surface works was 97% complete. Commissioning remains on track for the second half 2024.

  • Construction works for the concentrator conversion remain on schedule. Commissioning is expected to be progressively completed from the fourth quarter 2024 through to the second quarter 2025.

  • Construction of primary crusher 2 commenced in December 2023 and is due to be completed by the end of 2025.

  • OTLLC’s 2023 Oyu Tolgoi Feasibility Study for the Lift 1 underground mine has been submitted to and is under review by applicable regulatory bodies in Mongolia. The Lift 1 underground mine incorporates the development of three panels (Panels 0, 1, and 2). The Hugo North Extension (“HNE”) deposit on the Entrée/Oyu Tolgoi JV Property is located at the northern portion of Panel 1.

  • Drilling programs to support a Lift 2 Pre-Feasibility Study are in progress. Mineralization from Lift 2 will be included in an updated resource model for Hugo North (including Hugo North Extension).