Liberty Gold Reports Phase 4 Metallurgical Column Leach Results and Final Phase 5 Metallurgical Drill Assays at its Black Pine Oxide Gold Project, Idaho

Liberty Gold Corp.
Liberty Gold Corp.

In This Article:

84.2% weighted average gold extraction1 from 36 column leach tests

Figure 1

Black Pine Oxide Column Test Results – All Phases
Black Pine Oxide Column Test Results – All Phases

Figure 2

Map of all Black Pine Bulk Sample and Metallurgical Core Locations
Map of all Black Pine Bulk Sample and Metallurgical Core Locations

VANCOUVER, British Columbia, March 14, 2024 (GLOBE NEWSWIRE) --  Liberty Gold Corp. (TSX: LGD; OTCQX: LGDTF) (“Liberty Gold” or the “Company”) is pleased to report results from Phase 4B and 4C metallurgical bottle roll and column testing of gold mineralization in 36 variability composites taken from the Black Pine Oxide Gold Project (“Black Pine”) in southeastern Idaho. Additionally, final assay results are released on the remaining 4 metallurgical core holes drilled in 2023 to provide samples for the Phase 5 metallurgical test program.

HIGHLIGHTS

  • 36 variability composites from the Phase 4B and 4C test programs were selected from large-diameter (”PQ”) drill core from Discovery Zone, F Zone, Tallman, M Zone, and C/D Zone, representing a range of sample types across lithology and gold (“Au”) grade.

  • Key results include:

    • 84.2% weighted average gold extraction1 from column leach tests for the 31 oxide composites.

    • Gold extractions ranged from 52.7% to 94.2% for the oxide composites.

    • >80% of leachable gold extracted within 10 days.

  • Metallurgical testwork results on 149 composites and six bulk samples over five years are highly consistent, showing rapid leach kinetics, predictable grade-recovery and size-recovery relationships.

  • Phase 5 composite selection and sample preparation is under way on an additional 25 variability composites from previously untested areas.

Jon Gilligan, President & Chief Operating Officer for Liberty Gold said,The results of this latest phase of metallurgical column testwork add key infill data to the gold recovery model at Black Pine. The consistency of results across all phases of test work is encouraging and demonstrates the predictable nature of gold recovery across this extensive Carlin-style oxide gold system. With more than 150 columns completed the test results provide a strong level of confidence for the proposed run of mine heap leach processing approach.”

BLACK PINE METALLURGICAL TEST WORK

Liberty Gold has completed multiple phases of metallurgical testing at Black Pine including:

  • Bulk sample column tests

    • Phase 1A2 (6 x 300 kilogram surface bulk samples):

      • 78.9% weighted average gold extraction, ranging up to 92.8%

  • Variability composite column tests (149 composites from PQ drill core)

    • Phase 1B3 (29 composites):

      • 82.9% weighted average gold extraction, ranging up to 94.5%

    • Phase 24 (45 composites):

      • 80.8% weighted average gold extraction, ranging up to 94.8%

    • Phase 3 (15 low-grade composites):

      • 65.2% weighted average gold extraction ranging up to 80.8% (see press release dated October 27, 2021)

    • Phase 4A (24 composites):

      • 86.9% weighted average gold extraction, ranging up to 95.8% (see press release dated March 22, 2023)

    • Phase 4B and 4C (36 composites):

      • 84.2% weighted average gold extraction, ranging up to 94.2%.