MID-PROJECT UPDATE FOR HYPROMAG USA FEASIBILITY STUDY

CALGARY, AB / ACCESSWIRE / July 15, 2024 / CoTec Holdings Corp. (TSXV:CTH)(OTCQB:CTHCF) ("CoTec") and Mkango Resources Ltd. (AIM:MKA)(TSX-V:MKA) ("Mkango") are pleased to announce the findings of the mid-project review for the bankable feasibility study ("Feasibility Study") for HyProMag USA, LLC, a Delaware corporation ("HyProMag USA"). Canada-based BBA USA Inc. ("BBA") and U.S.-based PegasusTSI Inc. ("PegasusTSI") have been engaged to complete the HyProMag USA bankable Feasibility Study to engineer and design its REE magnet recycling plants and a production facility in the United States.

The Feasibility Study will be completed during Q4, 2024. HyProMag USA has the potential to supply the U.S. market with a sustainable, long term domestic supply of neodymium/iron/boron (NdFeB) permanent magnets to enable the creation of secure, low carbon and traceable rare-earth supply chains.

The key findings are:

  • Feasibility Study is now 50 per cent complete:

o Technology and design requirements for HyProMag's ongoing commissioning of the Tyseley facility in the UK, and associated pilot plant design and operating criteria have been successfully transferred to the U.S.-based Feasibility Study

  • Production:

o Targeted production capacity of a minimum of 500 tonnes per annum NdFeB magnets with the option to expand to 800 tonnes per annum NdFeB magnets production

o Opportunities to produce a range of additional NdFeB alloy products such as alloy powders, pellets and strip cast flakes are also being considered, as well as the recycling of swarf

  • Project Definition Rating Index ("PDRI"):

o Level of definition is more than sufficient to complete the current Feasibility Study and move to the Detailed Design following the completion of the current study phase

  • Value engineering:

o Design, layout and critical equipment sourcing have been challenged for reliable and cost-effective project implementation

o Identified opportunities to further optimize the project

  • Capital estimate:

o Association for the Advancement of Cost Engineering (AACE) Class 3 estimate to be confirmed in Q4 2024 with the completion of the Feasibility Study

  • Site selection:

o Four short-listed 'hub' site options located in Fort Worth, Texas have been identified. Approximate size of the hub site is 90,000 sq. ft

o Request for Proposal (RFP) process for Fort Worth has commenced to select preferred choice. Final site selection to be completed in Q4 2024