Soluna Announces Monthly Business Update

Soluna's Project Dorothy 2 - Under Construction (Photo: Business Wire)
Soluna's Project Dorothy 2 - Under Construction (Photo: Business Wire)

In This Article:

Soluna's Project Dorothy 2 - Under Construction (Photo: Business Wire)
Soluna's Project Dorothy 2 - Under Construction (Photo: Business Wire)

ALBANY, N.Y., October 09, 2024--(BUSINESS WIRE)--Soluna Holdings, Inc. ("SHI" or the "Company"), (NASDAQ: SLNH), a developer of green data centers for intensive computing applications including Bitcoin mining and AI, announced its September project site-level operations, developments, and updates.

The Company has provided the following Corporate and Site Updates.

Key Company Metrics:

The monthly metrics are now available here.

Corporate Highlights:

  • Term Sheets for Project Rosa – Soluna signed a term sheet with a renewable energy leader for Project Rosa, boosting capacity by 187 MW of sustainable energy for AI and Bitcoin mining.

  • CEO John Belizaire attended the 2024 Ai4 Conference – A recording of the panel "The AI Ecosystem: Hardware, Cloud, and Enterprise Integration" can now be viewed here.

  • New Blog – We unpack the problems and novel solutions to AI’s bottomless energy appetite. Read it here.

  • New Blog – We explore the convergence of artificial intelligence and renewable energy and the resulting innovative solutions. Read it here.

Key Project Updates:

Project Dorothy 1A (25 MW, Bitcoin Hosting) / Project Dorothy 1B (25 MW, Bitcoin Prop-Mining):

  • The Four Coincident Peak (4CP) period ended in September with our MaestroOS(?) control system successfully responding to all demand requirements.

  • Optimization efforts to include building insulation, heat shielding, and power infrastructure cooling solutions have been completed.

  • We successfully completed the summer program for our participation in ancillary services.

Project Dorothy 2 (48 MW, Bitcoin Hosting):

  • Site grading will be completed in the coming weeks.

  • Civil construction teams are in the process of pouring concrete pads for the initial phase of work with MDC fabrication underway so building erection can follow shortly after.

  • All long lead power infrastructure has been received.

  • Dates to complete the substation interconnection are in the process of being finalized with work slated to begin in December.

New Project Grace (2 MW at Dorothy 2, AI Cloud/Hosting):

New Project Ada (1 MW, AI Cloud with HPE):

  • 6 POCs in progress or completed with partners or potential customers.

  • New sales team in contract negotiations with several customers to fill the initial Cluster.

  • Demand for an additional 84 Nodes (or 672 GPUs) is on the waitlist.

  • Attracted leading aggregators to our Cloud platform.

Project Sophie (25 MW, Bitcoin Hosting with Profit Share, AI Hosting):

  • The site has continued to operate at a high level as cooler temperatures persist into the fall season.

  • Preparations are underway for an 8.8 MW fleet upgrade and 3.3 MW expansion of an existing customer to be completed in October.