Erdene Announces Q2 2024 Results and Provides Bayan Khundii Gold Project Update

Erdene Resource Development Corporation
Erdene Resource Development Corporation

In This Article:

HALIFAX, Nova Scotia, Aug. 08, 2024 (GLOBE NEWSWIRE) -- Erdene Resource Development Corp. (TSX:ERD | MSE:ERDN) (“Erdene” or the “Company”) is pleased to announce operating and financial results for the three months ended June 30, 2024, and to provide an update on progress at its Bayan Khundii Gold Project (“BK” or “Project”), being developed with Mongolian Mining Corporation (“MMC”). This release should be read in conjunction with the Company’s Q2-2024 Condensed Consolidated Interim Financial Statements and MD&A, available on the Company’s website and SEDAR+.

Peter Akerley, Erdene’s President and CEO stated, “The second quarter of 2024 was another productive period for Erdene as we made significant progress on both the exploration and development of our Khundii Minerals District projects in Southwestern Mongolia.”

He continued, “At the end of June, construction of the Bayan Khundii Gold Project stood at approximately 30% completion, with the process plant, the critical path facility, almost 40% constructed. All major mechanical equipment is now on site and construction has commenced on non-process infrastructure including the overhead transmission line. Though we have seen modest logistical and weather related delays the Project remains largely on schedule with first gold production projected in mid-2025.”

Mr. Akerley concluded, “Exploration over the past few months identified several new gold targets on both the Khundii and Zuun Mod licenses. Drilling is underway at Bayan Khundii to test targets west of the economic pit for expansion opportunities and to increase confidence of high-grade ore scheduled to be mined in the first year of production. Results of this work are expected in late Q3 2024.”

Q2-2024 Highlights and Significant Subsequent Events:

Bayan Khundii Construction Site – August 2024
Bayan Khundii Construction Site – August 2024


Images: Bayan Khundii Construction Site – August 2024

Bayan Khundii Gold Project

  • Reached approximately 30% construction progress at Bayan Khundii at June 30, 2024

    • Approximately US$60 million of total Project expenditures to the end of Q2 2024

    • Proceeding largely to schedule – construction expected to be substantially complete by the end of 2024 and first gold production in mid-2025

    • Process plant, the critical path facility, was ~40% complete at quarter end with critical mechanical equipment installation underway, focused on the SAG and ball mills

    • Almost 500 personnel on-site at quarter end achieving ~1,500,000 construction hours to date without a lost-time or environmental incident

  • Advanced community development and local employment stakeholder programs

    • Local Cooperation Agreement in place to support 2024 community development programs

    • Recruitment and training of Bayan Khundii mine workforce well advanced with 120 local residents completing mining equipment operator training at MMC’s UHG mine

    • Environmental Management Plan and the Gobi Bear conservation programs well progressed