Millennial Potash Completes Positive PEA with After-Tax NPV(10) of $1.07B and IRR of 32.6% for its Banio Potash Project

In This Article:

Vancouver, British Columbia--(Newsfile Corp. - April 23, 2024) - Millennial Potash Corp. (TSXV: MLP) (OTCQB: MLPNF) (FSE: X0D) ("MLP", "Millennial" or the "Company") is pleased to announce the completion of a Preliminary Economic Assessment ("PEA") on its Banio Potash Project. The PEA was completed by Micon International ("Micon") in partnership with Agapito Associates Inc. ("Agapito") and yielded the following highlights:

  • Optimal annual production rate of 800,000 Tonnes per Year (TPY) of primarily granular K60 Muriate of Potash (gMOP)

  • $1.07B after-tax NPV(10) and 32.6% IRR

  • $480M initial CAPEX estimate, including $62M in Contingency

  • Estimated $61/T gMOP OPEX

Positive evaluations also modelled for 400,000 TPY and 600,000 TPY were also completed as part of the PEA. All dollar amounts are in US dollars unless stated otherwise. Highlights of the PEA are presented in Table 1.

Farhad Abasov, Millennial's Chair, commented "We are extremely pleased with the results of the PEA on the Banio Potash Project and it has confirmed our belief that the project is very robust and has significant economic potential. The CAPEX for the 800,000 TPY optimal case is a very competitive $480M and the OPEX at approximately $61/tonne MOP reflects an expected overall low-cost structure which would make Millennial's Banio Potash Project competitive with the lowest cost producers in the sector. Moving forward the Company plans to complete a MRE update in H2 2024 followed by the completion of early engineering studies and the initiation of a Feasibility Study and Environmental Impact Assessment."

Table 1 PEA Highlights

Line Item

Unit

 

Production Rate MOP

t/a

800 k TPY

Total Initial CAPEX

US$ million

480

Capital Intensity

US$/t

600

Total OPEX LoM

US$/t

61

Pre-Tax NPV10

US$ million

1,680

Pre-Tax IRR

%

41

Post-Tax NPV10

US$ million

1,071

Post-Tax IRR

%

32.6

gMOP Price (Avg-25 years)

US$/t

387

Shipping Cost-Brazil

US$/t

22

NaCl price (99% purity)

US$/t

100

Payback

Years

1.4

 

PEA Outline

The Banio Potash Project PEA is based on the Mineral Resource Estimate completed by ERCOSPLAN early in 2024 (see Press Release dated Jan. 16, 2024). The MRE is comprised of an Indicated Mineral Resource Estimate of 657M tonnes grading 15.9% KCl, and an Inferred Mineral Resource of 1.159B tonnes grading 16% KCl. The Indicated Mineral Resource equates to approximately 104.6M tonnes of KCl and the Inferred Mineral Resource equates to approximately 185.3M tonnes of KCl.

The PEA utilizes both the Indicated and Inferred Mineral Resources in its mining production scenario. The PEA is preliminary in nature, and includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the PEA will be realized.